KISHTWAR: With the Chenab River‘s diversion through the Diversion Tunnels at Drabshalla, the 850 MW Ratle HE Project in Jammu and Kashmir has reached a significant milestone. The river diversion will make it possible to isolate the dam region at the riverbed and begin the crucial task of digging and building the dam. In order to support the project’s efforts to meet its May 2026 projected commissioning date, it will expedite project construction activities and help minimise delays. R K Vishnoi, the Chief Medical Director of NHPC, officially opened the River Diversion event. H Rajesh Prasad, the Principal Secretary (PDD); I D Dayal, the Chairman of RHPCL; Pankaj Mangotra, the MD of JKSPDC; NHPC Directors; A K Nauriyal, the CEO of RHPCL; and other dignitaries from NHPC and GoJK were present. Ratle Hydroelectric Power Corporation Limited (RHPCL), a joint venture between NHPC Limited and GoJK with a 51:49 percent stake, is responsible for carrying out the Ratle Project. The 850 MW Ratle HE project is located in the Kishtwar District on the Chenab River. The project received CCEA approval from the Indian government in February 2021, with a total estimated cost of Rs 5281.94 crore.